Residence Hall Update 11/17/20

Progress on the new residence hall continues, with many exterior items nearing completion.
In Tower B, flooring is complete, elevators are being installed, and ceramic tile is being set.

In Tower C, millwork is being set, walls are being textured, and elevators are being installed.

In Tower A, work on the lobby is ongoing, drywall is being installed and finished, walls on the 3rd and 4th floors are being painted, and ceramic work in public restrooms is ongoing.

All exterior glass, metal panels, and masonry is expected to be complete by the end of November.