Residence Hall Update 9/30/2020

Progress continues on the new residence hall.
Plumbing fixtures are being installed in Tower B.  Flooring is complete on 3rd and 4th floors.  In Tower C, the brickwork is 95% complete, and drywall is being floated and primed.  In the Flex Tower, drywall on 3rd and 4th floor is being painted, the reading nooks are being detailed, and the hood and grease duct have been installed for the demonstration kitchen.
Back

Louisiana School for Math, Science, and the Arts

© 2024 LSMSA All Rights Reserved